Skip to content
How To Buy Plots

Due Diligence

What Utilities Does the Land Have? How to Check Before You Buy

Listings say utilities are available. Learn what that really means, how to confirm electric, water, sewer, gas, and internet in writing, and what it costs to bring in what is missing.

By KenLast reviewed 13 min read

This guide contains affiliate links. If you buy through one, we may earn a commission at no extra cost to you. It never changes what we recommend. How this works.

Key takeaways

  • At the road, at the property line, and connected are three different things. Only connected means service exists today. Ask which one the listing means for each utility.
  • Find the electric utility that serves the parcel and get a written line extension estimate. Florida's state service area maps, for example, say their boundaries are approximations, and free-footage allowances differ by utility.
  • A water or sewer availability letter is not a commitment to serve, and it expires. Miami-Dade County's letter holds for 30 days. Ask for the connection and capital fees in writing.
  • The FCC National Broadband Map lists a provider only where it reports a routine installation within 10 business days with no line-extension charges. Check the exact address, then call the provider.
  • HomeGuide's 2026 guide puts a full utility hookup on vacant land at $9,000 to $34,500 or more, and Angi's at $6,500 to $30,000. Distance to the nearest line drives the number.
  • Make the purchase contingent on utility availability and cost, and get every answer from the utility in writing before the deadline.
In this guide

A land listing says utilities are available. The photos show a power pole by the road. What the listing does not say is whether that pole can serve your building site, where the water main ends, or whether any company will install internet at that address.

Utilities are often the largest cost between buying land and living on it, and the bill depends mostly on how far the parcel sits from the nearest line. Two parcels can look identical in a listing and differ by thousands of dollars in what it takes to turn the lights on.

Three phrases that sound alike

Five utilities matter: electricity, water from a public system or a well, sewer or septic, natural gas or propane, and internet and cell. For each one, a parcel is in one of three states, and listings blur them together.

At the road. A main or primary line runs in the public right-of-way along the frontage. Reaching your building site from it means a line extension, a lateral, a transformer, or a tap, mostly at your cost.

At the property line. The line reaches the edge of the parcel, which is where many utilities draw the line for available. Charlotte County, Florida, for example, treats a home as a mandatory sewer connection once "a wastewater collection line exists in an easement or right-of-way that abuts the property line" and gives the owner 180 days to pay the fees and connect. Available in that sense means you can connect, and in Charlotte County it means you must. Florida law backs that up: under s. 381.00655(1)(a), the owner of a properly functioning septic system generally must connect to an available sewer "within 365 days after written notification" that it is available, so a parcel sold as septic can carry a future sewer bill.

Connected. A meter is set, the tap or capital fee is paid, and an account can be opened. Only this stage means service exists today.

Internet has a federal test of its own. Under the FCC's Broadband Data Collection rules, a provider reports fixed service at a location only where it has built out its network and can perform a standard broadband installation with no network-extension charges, through "routine installation that can be completed not later than 10 business days after the date on which the service request is submitted."

Where the utility's line stops and your money startsA cross-section from the road to the building site marks three stages. At the road, a main or primary line runs in the public right-of-way and nothing touches the parcel. At the property line, the line reaches the parcel edge but there is no meter, tap, or service; Charlotte County, Florida treats a sewer collection line in an easement or right-of-way abutting the property line as a mandatory connection, and the FCC map lists an internet provider only where routine installation fits in 10 business days with no line-extension charges. Connected means the meter is set and the tap is paid; Orange County, Florida charges $2,790 per water ERC and $5,270 per wastewater ERU, and a meter base and 200-amp panel run $1,800 to $6,000 by Utility Cost Guide's October 2026 estimate. For electric, Suwannee Valley Electric Cooperative credits each residential extension with the average cost of 1,200 feet of overhead primary, $10,946 for January 2026, and past any allowance Utility Cost Guide estimates $6.50 to $30 per foot.Where the utility's line stops and your money startsThree phrases that sound alike. The distance between them is what you pay to close.Road right-of-wayYour parcelProperty linePole, primary lineUtility's allowance or creditSVEC: 1,200 ft of overhead primaryBeyond the allowance: you pay$6.50 to $30 per ft (Utility Cost Guide)line extensiontransformerservice dropmeter1231. At the roadA main or primary line runs inthe public right-of-way. Nothingtouches your parcel yet.To close the gapElectric: line extension, thentransformer, service drop orlateral, meter base and panel.Water or sewer: a lateral fromthe main, plus the utility's fees.Ask the utility, in writingWho serves this parcel, and whatis the estimate to the site?2. At the property lineThe line reaches the parcel edge,but no meter, tap, or service yet.Sewer: Charlotte County, FLA collection line in an easementor right-of-way that abuts theproperty line. That triggers amandatory connection.Internet: the FCC map testA provider may list a locationonly where routine installationfits in 10 business days with noline-extension charges.3. ConnectedMeter set, tap paid, service on.Water, sewer: Orange County, FLCapital charges of $2,790 perwater ERC and $5,270 perwastewater ERU (as of Oct. 2026),before any pipe is laid on the lot.Electric: the customer sideMeter base and 200-amp panel,$1,800 to $6,000 (Utility CostGuide estimate, Oct. 2026).Electric: the allowance decides the bill between stages 1 and 3Suwannee Valley Electric Cooperative (north Florida) credits each residential extension with the average cost of1,200 ft of overhead primary, $10,946 for January 2026. The member pays any job cost above the credit.Past any allowance, Utility Cost Guide estimates $6.50 to $30 per ft, with $15 as a planning figure (Oct. 2026).Sources: SVEC Policy 205.00, rev. Jan. 23, 2026; Utility Cost Guide, reviewed Oct. 2, 2026;Orange County, FL, Utilities Permitting Fees; Charlotte County, FL, Sewer Service; 47 CFR 1.7001(a)(19).Not to scale. Estimates are not quotes. Confirm every fee with the utility that serves the parcel.
The three stages a listing blurs together, and where the cost sits in each one. Not to scale.

The right-of-way line and the parcel line can be a few steps apart, and the cost difference is the whole extension. A mapping app such as Regrid shows where the boundary sits relative to the road and the poles, and how to find property lines covers the rest.

What listing phrases really mean

Listings are written to sell, and each utility needs its own answer.

PhraseWhat it usually meansThe question that pins it down
Utilities availableSome line exists somewhere nearbyWhich utilities, where does each line stop, and has a connection ever been made?
Power nearby or at the roadA distribution line runs along the roadWhich utility, how far from the pole to my building site, and what is the written estimate?
Water or sewer availableA main is near the parcel, with a fee and a lateral between you and serviceWill the utility issue an availability letter, and what are the fees?
Gas in the areaThe gas company serves the ZIP codeIs there a main on this road, and what does an extension cost?
High-speed internet availableA provider claims the areaWhich provider, which technology, and will it install at this address within 10 business days?

Even a utility's own ZIP code check is area-level. Peoples Gas, a Florida natural gas distributor, tells a user with a positive result to call "to see if it's in your neighborhood" anyway. The ZIP is not the parcel.

How to verify each utility

Electricity: find the utility, then get a written estimate

Electricity comes from an investor-owned utility, a municipal utility, or a rural electric cooperative, and assigned territory decides which one serves a parcel. State utility commissions usually publish territory maps. Florida's Public Service Commission posts one for each kind, and each carries the same warning: "Service areas are approximations. Information on this map should be used only as a general guideline. For more detailed information, contact individual utilities."

Then ask that utility for a written line extension estimate to the spot where you plan to build. Utilities often absorb part of the cost through a free-footage allowance or a construction credit, and policies differ widely. Suwannee Valley Electric Cooperative in north Florida credits each residential extension with the "Average cost to build 1,200 feet of overhead primary" as its policy puts it, a credit set at $10,946 for January 2026, and the member pays any job cost above it. Its estimates are valid for six months. Utility Cost Guide, reviewed October 2, 2026, says allowances vary so much that "the same 500-foot run can cost nothing with one utility and $7,500 or more with another."

Best for: Measuring the run from the nearest pole to the building site

Measuring wheel

Distance is the one cost driver you can measure yourself. Walk the route and compare it to the utility's allowance. The utility's engineer will measure the actual route, so use your number to budget, not to argue.

See options on Amazon

See the cost to run electricity to land for more.

Water and sewer: the availability letter and the fees

A public water or sewer utility can tell you whether a main is near the parcel, whether it has capacity to serve you, and what it will charge. Ask for all three in writing. Many utilities issue a will-serve letter or letter of availability. Two examples show the range.

Miami-Dade County's letter is informational: "This letter only advises you that water and sewer mains are available to service the project." Its conditions hold for 30 days, and it gives no vested right to service. Coachella Valley Water District in California issues its letters after connection fees are paid, and they "shall remain valid for eighteen (18) months from the date of issuance" unless a permitting agency requires an earlier expiration. If a seller hands you a letter, check the date and read exactly what it promises.

Two Florida counties show the fee scale.

Fee, single-familyWaterWastewaterSource
Pasco County connection fee, Oct. 1, 2026 to Sep. 30, 2027$1,801 ($1,351 for water with reclaimed)$3,404Pasco County Utilities
Orange County capital charge$2,790 per ERC$5,270 per ERUOrange County Utilities, as of Oct. 2026

Orange County's two charges add up to $8,060 before any pipe is laid on the lot. Pasco's fees step up each October, so ask for the schedule in effect when you expect to connect. Impact fees are separate and come at the building stage. In Florida, for impact fees adopted or increased after July 1, 2026, the Impact Fee Act says collection "may not be required to occur earlier than the date of issuance of the building permit" for the property.

County GIS can show service areas before you call. Pasco County's Water Service Areas layer "Includes all private and municipal water service providers" and has a wastewater companion, and many counties publish something similar.

No public service: wells and septic

Where no main is within reach, water means a well and sewer means septic, and both shift responsibility to you. The EPA states it plainly: "The quality and safety of drinking water from private domestic wells are not regulated by the Federal Government under the Safe Drinking Water Act nor by most state governments and laws." The county health or environmental office issues well and septic permits, and the soil decides whether septic is possible at all. Read what a perc test is before buying septic-dependent land, and see drilling a well and septic system cost and types for costs.

Gas: natural gas or propane

Ask the gas company whether a main runs on your road and what an extension costs. HomeGuide's January 2026 guide notes that "Some gas companies cover the installation costs up to a specified footage." Without a main, the answer is propane delivered to a tank on the property, so ask a local supplier about delivery and the cost to set a tank. If a tank is already there, find out who owns it. North Carolina's LP-gas regulator says that in that state, "Most of the time in North Carolina, when a propane company sets a tank, they keep ownership of it. This is especially true for above ground tanks." Practice varies by state, so ask whose tank it is.

Internet: the FCC map, then the provider

Start with the FCC National Broadband Map and enter the exact address or place the pin on the parcel. For fixed service it shows "which providers report making broadband service available at that location and the types of service or technologies and the maximum advertised download and upload speeds they each offer." NTIA's January 2024 BEAD guidance counts fiber, cable, DSL, and fixed wireless on licensed or hybrid spectrum as reliable broadband service, and the rest as alternative technology, which "includes unlicensed fixed wireless (ULFW) and low-earth orbit satellites (LEOs)." That is a funding classification, not a consumer rating, but a parcel with only those options listed has no wired choice.

OptionHow to checkWhat to watch
Fiber, cable, DSLFCC map, then the providerInstallation within 10 business days at the standard fee
Fixed wirelessFCC map, then a provider site checkWhether the spectrum is licensed, and the provider's own site check
Satellite, including StarlinkThe provider's map, such as the Starlink availability mapEnter the exact service address, not the nearest town

If a provider refuses, quotes more than its standard installation fee, or cannot schedule within 10 business days, the map was wrong for that location, and those are among the FCC's listed grounds for an availability challenge:

  • "Provider failed to schedule a service installation within 10 business days of a request"
  • "Provider requested more than the standard installation fee to connect this location"
  • "Provider denied the request for service"

A challenge corrects the map. It does not get you internet.

Cell signal: test it where the house will go

The FCC map's mobile layer shows where a phone should connect outdoors or in a moving vehicle, and "the map does not show indoor coverage." The only reliable check is to stand at the building site with the phones you actually use. The FCC Speed Test App is the FCC's own tool, and the on-the-ground tests it records are the evidence the FCC requires from individual consumers to support a mobile coverage challenge.

Best for: A building site with a weak but measurable signal

Cell signal booster

A booster amplifies a signal that already reaches the site and cannot create one, so run the speed tests first. Check carrier compatibility before you buy.

See options on Amazon

What it costs to bring in what is missing

Dated ranges from cost guides are the best public starting point. Every one is an estimate, not a quote.

ItemRangeSource and date
All utilities on vacant land$9,000 to $34,500 or moreHomeGuide, January 2026
All utilities, national average$20,400, with most spending $6,500 to $30,000Angi, updated September 2026
Electric from the road to the house$2,500 to $12,500, or $5 to $25 per linear footHomeGuide, January 2026
Well, remote property$5,000 to $10,000Angi, updated September 2026
Septic system, remote property$3,400 to $11,500Angi, updated September 2026
Water line from the main$25 to $200 per linear foot, or $1,000 to $6,000 or more with municipal feesHomeGuide, January 2026
Sewer line$50 to $200 per linear foot, or $1,600 to $10,900 or more with connection feesHomeGuide, January 2026
Natural gas line$350 to $2,000, or $15 to $50 or more per linear footHomeGuide, January 2026
Propane tank installed$700 to $5,700HomeGuide, January 2026

The two headline totals do not match, and that is the honest picture. Use them to decide whether a parcel deserves a closer look, and the utility's written estimate to decide whether to buy. For clearing, a driveway, and permits on top, see what it costs to develop raw land.

Put utilities in the contract

Two protections belong in every land offer.

A contingency. Make the purchase depend on your being satisfied with utility availability and cost within a stated period. The Florida Realtors Vacant Land Contract builds this in: its Due Diligence Period, 30 days if the blank is left empty, lets the buyer investigate "availability of access to public roads, water, and other utilities" and, if the property is unacceptable and written notice reaches the seller on time, cancel with the deposit returned. The same form offers a No Due Diligence Period box. Checking it declares the buyer satisfied "that either public sewerage and water are available to the Property or the Property will be approved for the installation of a well and/or private sewerage disposal system" along with zoning and other restrictions. Check that box only if you have already done the work.

Written answers. Get the territory confirmation, the estimate, the availability letter, and the fee schedule in writing, and keep them with the contract.

Confirm the contingency wording with a licensed real estate attorney in your state, since forms and deadlines differ. See how to make an offer on land for the other contingencies.

Who to call: a one-page checklist

Electricity. The state utility commission map or county GIS for the serving utility, then that utility's new-service desk for a written estimate, the allowance or credit, and its expiration.

Water. The water utility for an availability letter, capacity, fees, and where the main ends. The county health or environmental office for well rules if there is no public water.

Sewer. The sewer utility for an availability letter, mandatory connection rules, fees, and planned expansions. The county health or environmental office for septic requirements if there is no public sewer.

Gas. The gas distributor for whether a main is on the road and the extension charge. A propane supplier for delivery, tank cost, and who owns any tank on site.

Internet and cell. The FCC National Broadband Map, then each listed provider for whether it will install at this address within 10 business days at the standard fee. The satellite provider's map for the exact address. Your own phone at the building site with the FCC Speed Test App.

Everyone else. The seller for copies of any letters or estimates, and the county building department for impact fees.

See the land due diligence checklist and the free checklist for the rest.

The bottom line

Utilities available means almost nothing until you know which utilities, where each line stops, and what the utility will charge to reach your building site. Find the utility, get the estimate and the availability letter in writing, check the FCC map and then call the provider, and stand on the site with your phone. Put a utility contingency in the offer so the answers can change your price, or your mind, before your deposit is at risk.

Frequently asked questions

What does utilities available mean in a land listing?
Usually it means some line exists near the parcel, often in the road right-of-way. It rarely means the parcel has a meter, a tap, or an account. Ask the seller which utilities, where each line stops, and whether a connection has ever been made. Then confirm each answer with the utility itself and get it in writing.
How do I find out which electric company serves a parcel?
Start with your state utility commission's service area map or the county GIS, then call the utility to confirm. Florida's Public Service Commission publishes maps of investor-owned, municipal, and cooperative electric territories, but the maps themselves say the boundaries are approximations and tell you to contact the individual utility.
How much does it cost to run utilities to vacant land?
It depends on the distance to the nearest line and which utilities you need. HomeGuide's January 2026 guide puts the total at $9,000 to $34,500 or more. Angi's guide, updated September 2026, puts the national average at $20,400, with most people spending $6,500 to $30,000. A written estimate from each utility is the only number that counts.
How do I check internet availability on rural land?
Enter the exact address or location in the FCC National Broadband Map. It lists each provider that reports fixed service there, the technology, and the maximum advertised speeds. A provider should report a location only where it can complete a routine installation within 10 business days with no line-extension charges. Call the provider to confirm before you rely on it, and check the Starlink availability map for the exact address if nothing wired or fixed wireless shows up.
Can I make my offer depend on utilities being available?
Yes. Write a due diligence or feasibility contingency that lets you cancel and get your deposit back if the utilities, costs, or approvals are not acceptable. The Florida Realtors Vacant Land Contract, for example, has a due diligence period that covers availability of access to public roads, water, and other utilities. Confirm the wording with a licensed real estate attorney in your state.

Sources

  1. Sewer Service, Charlotte County Utilities, Charlotte County, Florida
  2. Florida Statutes 381.00655, Connection of existing onsite sewage treatment and disposal systems to central sewerage system; requirements, Florida Legislature
  3. 47 CFR § 1.7001, Scope and content of filed reports, Cornell Legal Information Institute, Code of Federal Regulations
  4. 47 CFR § 1.7004, Scope, content, and frequency of Broadband Data Collection filings, Cornell Legal Information Institute, Code of Federal Regulations
  5. Fact Sheet: National Broadband Map, Federal Communications Commission
  6. Broadband Data Task Force Releases Pre-Production Draft of the National Broadband Map; Announces the Start of the Broadband Availability Challenge Processes (DA 22-1210), Federal Communications Commission
  7. BEAD Reliable Broadband Service & Alternative Technologies Guidance, National Telecommunications and Information Administration, U.S. Department of Commerce
  8. Starlink Availability Map, Starlink
  9. Investor-Owned Electric Utilities, Municipal Electric Utilities, and Rural Electric Cooperatives: Approximate Company Service Areas, Florida Public Service Commission
  10. Policy Number 205.00, Line Extension, Suwannee Valley Electric Cooperative, Inc.
  11. Water or Sewer Letter of Availability Application (LOA), Miami-Dade County Water and Sewer Department
  12. Will-Serve Letters for Water & Sewer, Coachella Valley Water District
  13. Rates, Fees And Charges, Pasco County Utilities, Pasco County, Florida
  14. Utilities Permitting Fees, Orange County Government, Florida
  15. Florida Statutes 163.31801, Impact fees; short title; intent; minimum requirements; audits; challenges, Florida Legislature
  16. Layer: Water Service Areas (ID: 4), PCU_Public_Layers MapServer, Pasco County Utilities GIS, Pasco County, Florida
  17. Private Drinking Water Wells, U.S. Environmental Protection Agency
  18. Standards - LP-Gas FAQ for Consumers, North Carolina Department of Agriculture and Consumer Services
  19. ZIP Code Check, Peoples Gas (TECO Energy), Florida
  20. Vacant Land Contract (VAC-14xxx Rev 8/24), Florida Realtors
  21. How Much Does It Cost to Get Utilities on Land? (2026), HomeGuide
  22. How Much Does It Cost to Get Utilities on Land? [2026 Data], Angi
  23. Cost to Run Power to Property in 2026: 200, 500 and 1,000 Feet, Utility Cost Guide

This guide is general education, not legal, financial, or tax advice. Rules and costs vary by state, county, and parcel. Confirm the details for your property with the county and a licensed professional before you rely on them.

Due Diligence

Landlocked Property: How to Confirm Legal Access Before You Buy

The only road to the land crosses a neighbor's property. Learn the difference between a path and a legal right, how to verify access in the title work, and your options if the parcel is landlocked.

13 min readReviewed September 29, 2026