Cost to Run Electricity to Land in 2026, and When Solar Makes More Sense
What the power company charges to extend a line to a building site, how free footage and CIAC formulas work, dated 2026 per-foot costs, and when off-grid solar beats a long extension.
By KenLast reviewed 13 min read
This guide contains affiliate links. If you buy through one, we may earn a commission at no extra cost to you. It never changes what we recommend. How this works.
Key takeaways
- The utility's written estimate is the only number that matters. HomeGuide and Utility Cost Guide put a line extension at $5 to $30 per foot in their 2026 guides, but a free footage allowance can make the same 500-foot run cost nothing at one utility and thousands at another.
- Utilities commonly charge a contribution in aid of construction, or CIAC, for new line. Formulas differ: Florida's investor-owned utilities net four years of expected revenue against the job cost, Clay Electric nets five, and Pedernales Electric in Texas bills the full cost before it builds.
- Underground costs more and the owner often digs. Clay Electric may charge the full difference between underground and overhead, and Pedernales makes the applicant supply the trench, backfill, and conduit.
- You also pay for the meter base and service panel on your side of the meter, $1,800 to $6,000 by one October 2026 estimate, plus the county electrical permit.
- A whole-home off-grid solar system averaged $45,000 to $65,000 in This Old House's 2025 guide, and EnergySage's 2026 examples run past $115,000. It only beats a long extension, and batteries need replacing every five to ten years.
- The federal Residential Clean Energy Credit is not available for property placed in service after December 31, 2025, according to the IRS page as of July 2026. Do not count on it for a 2026 install.
In this guide
Land listings love to say power is at the road. That means a distribution line runs along the frontage, and nothing more. Bringing that power to your building site can be the largest bill after the land itself.
The utility that holds the territory sets the price under its own line extension policy. Some build the first quarter mile free. Others bill every foot. The same 500 feet can cost nothing or many thousands of dollars.
How a line extension works
The utility builds from its existing line to a new meter. You build from the meter into the structure. The tariff spells out who does what.
The request and the estimate
You apply with the utility that serves the parcel; territories are assigned, and in Florida the Public Service Commission approves territorial agreements among cooperatives, municipal utilities, and other electric utilities. To find yours, see what utilities are available on land.
The utility designs the extension and returns an estimate. Pedernales Electric Cooperative, in the Texas Hill Country, under its tariff effective October 1, 2026, promises an estimated completion date and a Cost Calculation for all charges whenever facilities must be built. Get it in writing before you close.
Overhead or underground
Overhead line hangs on poles, which HomeGuide's January 2026 guide prices at $1,200 to $5,600 each. Underground line runs through conduit in a trench, costs more, and the owner often digs. Pedernales makes the underground applicant responsible for "all trenches and backfill, sectionalizing cabinets, concrete work associated with pad-mounted facilities" plus all conduit and vaults. Clay Electric Cooperative in north-central Florida may collect "the total difference in cost for providing underground service instead of overhead service".
Transformer, meter base, and service entrance
The utility supplies the transformer. Angi's guide, updated September 21, 2026, prices a new one at $3,000 to $7,000; whether that lands on your bill depends on the tariff. The meter base, service entrance, and main panel are yours. Utility Cost Guide's October 2026 estimate says: "The customer-side meter base and 200-amp panel add $1,800 to $6,000." HomeGuide puts the electrician at $50 to $130 per hour. The utility sets the meter, usually after the county or city building department has inspected your side.
At Clay Electric the last leg is buried by default: "All new individual services to the meter location shall be underground unless otherwise approved by the Cooperative." The member installs the conduit and the co-op pulls the wire at no charge. The primary line behind it is still charged under the formulas below.
Easements across neighboring land
Pedernales builds extensions "within private easements granted on the Cooperative's standard form", and the applicant clears the easement on their own land. If the shortest route crosses a neighbor's parcel, it follows that the neighbor must grant the utility an easement first, and a neighbor can refuse. Price that risk before you buy. See our guides to easements and landlocked property, and have a licensed real estate attorney in your state review any easement you need or grant.
How utilities price the extension
Utilities commonly call the charge a contribution in aid of construction, or CIAC. Clay Electric's tariff, effective June 1, 2023, puts it this way: "Such contributions will be in addition to any distribution charge imposed by the Cooperative."
Free footage allowances
Pioneer Electric Cooperative in southwest Kansas publishes the clearest example: "For up to a ¼ mile of line there is NO line extension cost." Beyond 1,320 feet it charges $6.50 per foot for single-phase overhead line and $10.00 per foot underground. Its half-mile example is 1,320 billable feet, $8,580 at list, shown as $6,864 in a lump sum or $129 a month for 60 months. The page is undated, so treat these as the rates published when this guide was reviewed.
Allowances can vanish. Until June 2023, Clay Electric exempted residential overhead primary lines of 400 feet or less, and underground lines of the same length when the member installed the conduit. Its 2023 revision struck that language so that "a calculation will be performed for every project".
Job cost minus expected revenue
Both Florida formulas net the cost to build against the revenue the utility expects from the new meter. Clay Electric takes the estimated cost of new poles, conductors, and fixtures, excluding transformers, service drops, and meters, and subtracts five years of expected non-fuel energy revenue. Florida's investor-owned utilities, such as FPL, Duke Energy Florida, and Tampa Electric, follow Public Service Commission Rule 25-6.064, which subtracts four years. That rule covers investor-owned utilities only; cooperatives file their own tariffs. A full-time home earns a bigger revenue credit than a weekend cabin, so the cabin owner pays more.
Full cost up front
Pedernales Electric charges the whole bill before it builds. The residential applicant pays all costs "to extend electric service to the Point of Interconnection as a CIAC prior to construction", including primary conductors, transformers, and poles, with no footage allowance. "The Cost Calculation may expire or be re-calculated at the sole discretion of the Cooperative", and any overrun is billed at completion. Pedernales can set that policy because the Public Utility Commission's authority over cooperatives is limited to the short list in Utilities Code Section 41.004, so each co-op's board writes its own extension rules.
Refunds, true-ups, and payment plans
Under Florida's Rule 25-6.064, a customer of an investor-owned utility "may request a review of any CIAC charge within 12 months following the in-service date of the new or upgraded facilities", and when more customers are expected on the line, the utility prorates the CIAC over those expected within 3 years and credits their shares to the customer who paid. Pedernales takes the opposite position: payments for construction "are CIAC and are not refundable after construction." Ask which rule applies to you.
Clay Electric lets residential members pay monthly "over a one (1) to seven (7) year period, determined by the dollar amount, including appropriate interest".
What it costs in 2026
Three dated national cost guides give per-foot ranges. They are planning figures, and none knows your utility's allowance.
| Guide and date | Per foot | Other figures |
|---|---|---|
| HomeGuide, January 5, 2026 | $5 to $25 per linear foot; $2,500 to $12,500 road to house | Poles $1,200 to $5,600; trenching $5 to $12 per foot |
| Angi, updated September 21, 2026 | $5 to $15 per linear foot in the text; its table lists $4 to $12 | About $1,000 when lines reach the property line; transformer $3,000 to $7,000 |
| Utility Cost Guide, reviewed October 2, 2026 | $6.50 to $30 per foot, $15 planning figure | Meter base and panel $1,800 to $6,000 |
Utility Cost Guide makes the point that matters most: "Some utilities build the first 500 feet, or even the first quarter mile, at no charge, so the same 500-foot run can cost nothing with one utility and $7,500 or more with another."
The table below multiplies the two widest ranges by distance and sets Pioneer's formula beside them, with its underground figure computed from the $10.00 rate.
| Distance | HomeGuide, $5 to $25 per foot | Utility Cost Guide, $6.50 to $30 per foot | Pioneer Electric formula |
|---|---|---|---|
| 200 feet | $1,000 to $5,000 | $1,300 to $6,000 | $0 |
| 500 feet | $2,500 to $12,500 | $3,250 to $15,000 | $0 |
| 1,000 feet | $5,000 to $25,000 | $6,500 to $30,000 | $0 |
| 2,640 feet, half a mile | $13,200 to $66,000 | $17,160 to $79,200 | $8,580 overhead, $13,200 underground |
These figures leave out your side of the meter, the permit, and clearing the route.
Timeline and steps
- Get the estimate before you buy. Give the utility the parcel number and the building spot. Make the offer contingent on it if the number matters. See how to make an offer on land.
- Apply, pay any design fee, and secure easements.
- Pay the CIAC. Pedernales collects it before construction.
- Build your side and pass inspection. Clear the easement, dig the trench if the line is underground, and have a licensed electrician set the meter base, conduit, and panel.
- Construction and meter set. Pedernales aims to finish "within ninety (90) calendar days of fulfilling all applicable requirements", unless delayed by causes beyond its control. Ask your utility for its target.
Temporary construction power
At Pedernales, non-permanent service is paid entirely by the applicant: "one hundred percent (100%) of the cost of installation and removal of all necessary electric service facilities and equipment before any construction begins." A generator or portable power station can beat a temporary pole you pay to install and remove. If you will live on the land in an RV meanwhile, see mobile homes, tiny homes, and RVs on your land.
Best for: Pacing the distance from the nearest pole to your building site
Measuring wheel
Pace the route a line would follow to see whether you are inside an allowance before you call. The utility measures its own route, and its number is the one you pay.
Off-grid solar as the alternative
The University of Arizona Cooperative Extension states the case plainly: "In rural areas, the cost to install an electrical connection to a utility-line may be prohibitive." It describes a stand-alone system as solar modules, a charge controller, a deep-cycle battery bank, an inverter for AC loads, and a backup generator for cloudy stretches. In EnergySage's example below, the batteries are most of the cost.
What it costs
This Old House's guide, updated June 11, 2025, puts a whole-home off-grid system at $45,000 to $65,000 on average, "more than double the cost of traditional grid-tied systems". It lists DC-only systems at $6,000 to $10,000 for small uses such as an RV and full AC systems with a backup generator at $40,000 to $70,000.
EnergySage's guide, updated June 29, 2026, is blunter. Going off-grid "requires substantial battery storage, backup power, and careful planning around your energy use. For most homes, it's neither practical nor cost-effective." Its example comes to $157,949 for off-grid solar plus storage in Massachusetts and $115,945 in Arizona, against $45,208 and $44,139 grid-tied.
A plug-in electricity usage monitor measures what each appliance draws, the starting point for sizing a system.
Batteries, generators, and maintenance
The Arizona Extension's guidance: "A deep cycle battery should not be discharged beyond 50% of its state of charge (SOC)." Flooded lead-acid batteries cost the least but need maintenance; lithium-ion needs none and can last about 10 years, but costs the most. This Old House says the system "can last 25 years or more with proper maintenance", while "Solar batteries and charge controllers may need replacement after five to 10 years." That cycle is the hidden cost: a line extension is paid once, while off-grid batteries come back as a bill every five to ten years.
Best for: Backup charging for a battery bank, and power during construction
Dual-fuel inverter generator
Both This Old House and the Arizona Extension describe a backup generator as part of an off-grid system. A dual-fuel unit runs on gasoline or propane. It is a backup, not a primary source, and it belongs well away from any structure.
When solar beats a long extension
EnergySage says off-grid makes sense for homes with low consumption, remote properties where a grid connection is impractical or expensive, and people who want full independence. At $25 to $30 per foot with no allowance, an extension reaches the $45,000 bottom of This Old House's range at roughly 1,500 to 1,800 feet. At Pioneer's $6.50 per foot after a free quarter mile, it would take well over a mile. At the low end of the ranges, even half a mile costs less than the cheapest whole-home solar average.
If the written estimate plus your side of the meter comes in under a solar quote sized to your measured use, grid power is usually the better buy. If it runs past, solar deserves a serious look, and so does a smaller, lower-consumption home.
The federal solar tax credit in 2026
The IRS page for the Residential Clean Energy Credit, last reviewed July 4, 2026, states: "The Residential Clean Energy Credit equals 30% of the costs of new, qualified clean energy property for your home installed anytime from 2022 through December 31, 2025. The credit is not available for any property placed in service after December 31, 2025." And: "You must claim the credit for the tax year when the property is installed, not merely purchased." By that rule, equipment bought in 2025 but installed in 2026 would not qualify.
The same page still carries older language about a phase-out beginning in 2033, so treat the December 31, 2025 cutoff as the operative statement, read the IRS page before you sign a solar contract, and confirm with a tax professional. State and utility incentives are a separate question for your state energy office.
Solar generators and portable power
A solar generator is a battery in a box with an inverter and outlets. It suits camping on the land, an RV, a hunting cabin, or tools before the meter is set. It is not a whole-home system.
Popular Science's review, updated December 9, 2025, shows the limits. The Jackery Explorer 2000 Plus holds 2 kWh and can deliver up to 6,000 W, enough to run a welder, but "The battery will only last you about half an hour doing this (we tried it)". It kept a router running for several hours in an outage and can be chained with external batteries up to 24 kWh. Heavy continuous loads drain it fast.
Best for: Camping, an RV, a cabin, or tools during construction
Portable power station, about 2 kWh
Runs lights, chargers, a laptop, and a power tool in short bursts, not a house. Recharge it from a vehicle, a generator, or a folding solar panel matched to its input, and expect hours of runtime, not days.
The bottom line
The cost to run electricity to land is whatever the utility's tariff says it is, and nothing you read online replaces its written estimate. Get it before you buy, itemized by total, free, and billable feet, and add $1,800 to $6,000 for your side of the meter. Compare that with an off-grid solar quote sized to your measured use, batteries included, with no federal credit for a 2026 install. Within a few hundred feet of a line, the extension usually wins. Past half a mile, run both numbers. The other big costs are in what it costs to develop raw land, wells, and septic.
Frequently asked questions
- How much does it cost to run electricity to land in 2026?
- National cost guides dated 2026 put a line extension at $5 to $25 per linear foot (HomeGuide, January 2026) or $6.50 to $30 per foot (Utility Cost Guide, October 2026), plus $1,800 to $6,000 for the meter base and panel on your side. The real answer comes from the utility that serves the parcel. Ask it for a written estimate before you buy, because a free footage allowance can cut the bill to zero, or the full job cost can land on you.
- Will the power company run electricity to my land for free?
- Sometimes part of it. Pioneer Electric in Kansas builds the first quarter mile of single-phase line at no charge, then bills $6.50 per foot overhead. Clay Electric in Florida dropped its old 400-foot exemption in 2023 and now calculates a charge on every project. Pedernales Electric in Texas charges the full cost to the point of interconnection before building. The allowance depends entirely on the utility's tariff.
- Is off-grid solar cheaper than running power lines?
- Only for long runs. This Old House's 2025 guide puts a whole-home off-grid system at $45,000 to $65,000 on average, and EnergySage's June 2026 examples show $115,945 to $157,949 once enough batteries are included. At the top of that range, $30 per foot with no allowance, an extension reaches $45,000 at roughly 1,500 feet; at lower rates it stays cheaper much farther, and an extension has no batteries to replace every five to ten years.
- Is the federal solar tax credit still available in 2026?
- Not for new installs, according to the IRS. Its Residential Clean Energy Credit page, last reviewed in July 2026, states that the credit is not available for any property placed in service after December 31, 2025, and that the credit is claimed for the year the property is installed, not purchased. Check the IRS page and your state energy office for anything that has changed.
- Can I get temporary power on land while I build?
- Usually, at your cost. Pedernales Electric's tariff makes the applicant pay 100 percent of the installation and removal cost for any non-permanent service before work begins. Many builders run a portable power station or generator instead until the permanent meter is set. Ask the utility and the county building department what a temporary service pole requires.
Sources
- Residential Clean Energy Credit, Internal Revenue Service
- Clay Electric Cooperative, Inc. revised tariff sheets 5.0 to 5.31, FPSC Document No. 02962-2023, Clay Electric Cooperative, filed with the Florida Public Service Commission
- Fla. Admin. Code Ann. R. 25-6.064 - Extension of Facilities; Contribution in Aid of Construction, Florida Public Service Commission rule, via Cornell Legal Information Institute
- Florida Statutes 366.04 Jurisdiction of commission, Florida Legislature
- Tariff and Business Rules for Electric Service, Section 400 Facilities Extensions Policy, Pedernales Electric Cooperative, Inc.
- Texas Utilities Code Section 41.004, Jurisdiction of Commission, Texas Legislature, via texas.public.law
- Line Extension Cost, Pioneer Electric Cooperative
- How Much Does It Cost to Get Utilities on Land? (2026), HomeGuide
- How Much Does It Cost to Get Utilities on Land? [2026 Data], Angi
- Cost to Run Power to Property in 2026: 200, 500 and 1,000 Feet, Utility Cost Guide
- Guide to Off-Grid Solar System Costs (2026 Breakdown), This Old House
- Off-Grid Solar: Costs, Process, and Best Products in 2026, EnergySage
- Stand Alone Photovoltaic (PV) Systems: A Description & Function of System Components (az1983), University of Arizona Cooperative Extension
- The best solar generators for 2026, tested and reviewed, Popular Science
This guide is general education, not legal, financial, or tax advice. Rules and costs vary by state, county, and parcel. Confirm the details for your property with the county and a licensed professional before you rely on them.